Capital Projects Update
Capital Reserve Project Update
December 2025
Included Projects:
-
Phase 1 - Sed Permit Issued
-
Installation of Field Lighting on Mezaros
-
Replacement of the Turf on Mezaros
-
Resurfacing of the Oley Track
-
Removal of Casework in some High School Classrooms
-
Replacement of some Ground Floor Windows at the Middle School for Safety Reasons
-
Bathroom Upgrade of the First Floor Girls Bathroom in the High School
-
Paving of the Basketball Court on the Dows Lane Campus
-
Paving of the Play Area at Dows Lane on the East Side of the Building
Bids:
-
Electrical Bid to Support Field Lighting Project Received November 19 and to Be Awarded December 2
-
Bid Specifications for the Remaining Phase 1 Projects Are Currently Being Finalized
Timeline Updates:
-
Weather Permitting, Field Lights Installation to Be Completed by March 15, 2026
-
Track and Field Replacements Work to Begin in June 2026 After Spring Season Is Complete
-
Remaining Phase 1 Work to Be Completed Summer 2026